Merom Solar kWh Generation
Readings began on November 25, 2008

Select a start date:

  
Click on a column to see the 15-minute interval data
Chart.

Cumulative Totals:

Start date:  
Cumulative Total for to : kWh
End date:   
   


Equipment

Learn more about the equipment used at this site by viewing the Adobe Acrobat PDF files below.


3kW Solar Install
14 216 W Solar Panels $17,850.00
3kW Inverter 2,770.00
Mounting Hardware 2,531.60
DC disconnect/combiner 368.00
Grounding hardware 134
System display 425
Concrete 378.18
Shipping 900.00
Total Materials $25,215.68
Contractor labor (48.25 hours) $3,618.75
Helper time (47.75 hours) 2,287.50
Total Labor $5,906.25
   
Grand Total $31,121.93


Solar Panels Located at the Education Center near Merom in Sullivan County

Merom's solar panels located near the Education Center